Project Number: BCP-2

Project Status   |  Proposed

A feasibility study underway with completion and approval expected in May 2017. The study includes bathymetric surveys, wetland delineations, and sediment sampling including analyses for harmful contaminants. An open house and public input meeting will be held in February 2017 for residents to learn more about the project and for BCWMC and city staff to hear concerns and answer questions. If you wish to receive an emailed notification of the public meeting, please contact the BCWMC Administrator.


Project Funding   |   Not Grant Funded

Estimated project costs will be available with the completion of the feasibility study but are likely to be between $500,000 and $1,000,000. BCWMC capital projects such as this are typically funded through an ad valorum tax of all watershed residents. Some projects also receive county or state grant funds.


Project Description

This proposed project that will remove sediment that has collected in the main channel of the North Branch of Bassett Creek within Bassett Creek Park Pond and Winnetka Pond in the City of Crystal. The project will improve water quality downstream by trapping sediment in the pond, thus minimizing sediment passing downstream to Bassett Creek. Additional information will be available upon completion of the feasibility study in May 2017.

Project Announcements

Public Open House for Bassett Creek Park Pond & Winnetka Pond Dredging Project

February 16, 2017 - 5:30 pm - 7:30 pm

The Heathers Manor, Community Room (downstairs); 3000 North Douglas Drive in Crystal

You're invited to learn more about this proposed project at a public open house. BCWMC and city staff will be on hand to answer questions and collect input from the public.